Supply of materials and implementation of the operation of guardian structure and main structure of transition of line 6 to line 10.
the operation of guardian structure and main structure of transition of line 6 to line 10.
- Employer: Chilko company
- Client consultant: consulting engineers of Behro
- The contract start date: 95/07/15
- End date of the contract: 95/12/15
- Operation place of the project: Tehran
- Field: way – installations